Orden de Cambio de Construcción
Enmienda firmada a un contrato de construcción o mejoras al hogar: qué cambia, cuánto suma o resta al precio, el precio revisado del contrato, cuántos días añade al plazo y la confirmación de que todo lo demás sigue igual.
Elija su estado
Seleccione un estado para cargar las reglas legales correctas.
- Alabama
- Alaska
- Arizona
- Arkansas
- California
- Colorado
- Connecticut
- Delaware
- Distrito de Columbia
- Florida
- Georgia
- Hawái
- Idaho
- Illinois
- Indiana
- Iowa
- Kansas
- Kentucky
- Luisiana
- Maine
- Maryland
- Massachusetts
- Míchigan
- Minnesota
- Misisipi
- Misuri
- Montana
- Nebraska
- Nevada
- Nuevo Hampshire
- Nueva Jersey
- Nuevo México
- Nueva York
- Carolina del Norte
- Dakota del Norte
- Ohio
- Oklahoma
- Oregón
- Pensilvania
- Rhode Island
- Carolina del Sur
- Dakota del Sur
- Tennessee
- Texas
- Utah
- Vermont
- Virginia
- Washington
- Virginia Occidental
- Wisconsin
- Wyoming
Compare las reglas de Orden de Cambio de Construcción en los 50 estados
Cifras legales clave lado a lado. Haga clic en una columna para ordenar o escriba para encontrar su estado: cada nombre abre el generador específico del estado.
| Alabama | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
|---|---|---|---|---|
| Alaska | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Arizona | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Arkansas | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| California | Yes | Required | The change in price must be stated; the effect on the schedule or completion date… | A contractor may not collect payment for work not yet completed or for materials not… |
| Colorado | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Connecticut | Yes | Not stated in the statute; signing before the work starts is the practice the statute… | The change in price is not expressly mandated by the statute | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Delaware | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Distrito de Columbia | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Florida | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Georgia | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Hawái | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Idaho | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Illinois | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Indiana | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Iowa | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Kansas | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Kentucky | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Luisiana | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Maine | Yes | Not stated in the statute; signing before the work starts is the practice the statute… | The change in price must be stated | The home construction contract's down payment is limited by statute, and the limit is… |
| Maryland | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | A home improvement contractor may not require or accept a payment that is more than… |
| Massachusetts | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | A deposit taken before work begins may not exceed the greater of one-third of the… |
| Míchigan | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Minnesota | Yes | Not stated in the statute; signing before the work starts is the practice the statute… | The change in price must be stated | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Misisipi | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Misuri | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Montana | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Nebraska | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Nevada | Yes | Not stated in the statute; signing before the work starts is the practice the statute… | The change in price must be stated | The schedule of payments may never let the contractor receive more than 100 percent… |
| Nuevo Hampshire | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Nueva Jersey | Yes | Not stated in the statute; signing before the work starts is the practice the statute… | The change in price is not expressly mandated by the statute | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Nuevo México | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Nueva York | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | Every progress payment must bear a reasonable relationship to the amount of work to… |
| Carolina del Norte | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Dakota del Norte | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Ohio | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Oklahoma | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Oregón | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Pensilvania | Yes | Not stated in the statute; signing before the work starts is the practice the statute… | The change in price must be stated | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Rhode Island | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Carolina del Sur | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Dakota del Sur | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Tennessee | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Texas | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Utah | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Vermont | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Virginia | Yes | Not stated in the statute; signing before the work starts is the practice the statute… | The change in price must be stated; the effect on the schedule or completion date… | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Washington | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Virginia Occidental | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Wisconsin | Yes | Not stated in the statute; signing before the work starts is the practice the statute… | The change in price is not expressly mandated by the statute; the effect on the… | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
| Wyoming | Not required by a confirmed statute | No confirmed statutory rule; sign before the changed work starts so the extra is not… | No confirmed statutory content rule | No confirmed statutory limit on when a change order may be billed; pay for extra work… |
Ningún estado coincide; pruebe el código de dos letras.
Los valores están abreviados; abra la página del estado para ver la regla completa y su fuente.
Qué cubre este documento
- Número de la orden y el contrato que enmienda
- Contratista, número de licencia y propietario
- Dirección de la obra y fecha del contrato original
- Qué cambia, en palabras de ambas partes
- Por qué cambia: petición, condición oculta, código o diseño
- Precio detallado o suma alzada, sumada o restada
- Precio revisado del contrato tras todas las órdenes previas
- Días añadidos al plazo y nueva fecha de terminación
- Condiciones de pago solo de este cambio
- Confirmación de que el resto del contrato sigue vigente
Cómo usar este Orden de Cambio de Construcción en US
No se confirmó en your state una regla estatal que exija orden de cambio escrita, así que deciden la cláusula del propio contrato y el derecho general de contratos (Common law of contracts; state statute of frauds). Una orden de cambio no es un contrato nuevo: identifica el contrato original y su fecha, describe exactamente qué cambia, lo cotiza y dice qué efecto tiene en la fecha de terminación. Todo lo demás del contrato sigue vigente.
Cotice de forma verificable por el propietario. Las partidas —cantidad por precio unitario, mano de obra y materiales por separado— resisten una disputa; la suma alzada sirve para trabajos pequeños. Diga si el monto se suma o se resta y arrastre la aritmética: precio original, más el neto de las órdenes anteriores, más o menos esta, igual al precio revisado. Esa última cifra es la única que debe aparecer en la próxima factura, en la solicitud de desembolso del banco y en cualquier gravamen.
Trate plazo y dinero en el mismo documento. Escriba el efecto en días enteros, aunque sea cero: si lo deja en blanco suele regir la fecha original y el contratista queda en mora por un cambio que pidió el propietario. Sobre el pago no se confirmó un límite legal en your state; rige el contrato, y facturar a medida que se ejecuta el cambio evita problemas. El anticipo por material de pedido especial es la excepción razonable.
Firme antes de iniciar el trabajo del cambio y entregue copia al propietario el mismo día. Firmar primero es lo que hace probable la orden: el expediente muestra que el precio se pactó antes de empezar.. Guarde la orden firmada con el contrato, las facturas y las renuncias de gravamen.
Otros nombres
- orden de cambio
- orden de cambio de obra
- enmienda al contrato de construcción
- orden de trabajo extra
- modificación de contrato de obra
- adenda al contrato de construcción
Documentos relacionados
Orden de Cambio de Construcción en blanco por estado
gratis, sin cuenta · PDF + Word
Elija su estado ▾
- Alabama
- Alaska
- Arizona
- Arkansas
- California
- Colorado
- Connecticut
- Delaware
- Distrito de Columbia
- Florida
- Georgia
- Hawái
- Idaho
- Illinois
- Indiana
- Iowa
- Kansas
- Kentucky
- Luisiana
- Maine
- Maryland
- Massachusetts
- Míchigan
- Minnesota
- Misisipi
- Misuri
- Montana
- Nebraska
- Nevada
- Nuevo Hampshire
- Nueva Jersey
- Nuevo México
- Nueva York
- Carolina del Norte
- Dakota del Norte
- Ohio
- Oklahoma
- Oregón
- Pensilvania
- Rhode Island
- Carolina del Sur
- Dakota del Sur
- Tennessee
- Texas
- Utah
- Vermont
- Virginia
- Washington
- Virginia Occidental
- Wisconsin
- Wyoming
FormsByState ofrece plantillas de autoayuda e información general, no asesoría legal. No somos un bufete de abogados. Para su situación consulte a un abogado con licencia en su estado.