Utah Construction Lien Waiver and Release (2026)

Conditional or unconditional lien waiver for a progress or final payment, using your state's statutory form and mandated warning language where the law prescribes one.

Updated September 2026≈ 4 minReviewed against Utah Code § 38-1a-802 · Utah Code §§ 38-1a-101 et seq.
ENESRU中文UZ
Free to fill & preview · $9 PDF + WordBlank PDF (free, no account)
Sample first page of the Construction Lien Waiver and Release: title block and opening sections with blanks to fillView larger
What you'll get

Sample first page of the Construction Lien Waiver and Release. Your answers fill in the blanks; the clauses required in Utah are added automatically.

  • PDF
  • Word
  • Print
Sample first page of the Construction Lien Waiver and Release: title block and opening sections with blanks to fill

Sample first page of the Construction Lien Waiver and Release. Your answers fill in the blanks; the clauses required in Utah are added automatically.

This preview updates as you type. Blank fields show as ____ .

What this document covers

  • Conditional or unconditional, progress or final
  • Your state's statutory form where one is prescribed
  • The exact warning language the statute mandates
  • Claimant, customer and owner identification
  • Project name, job location, city and county
  • Job number and payment application number
  • Amount of the payment and the through date
  • Check maker, payee and payment reference
  • Retention, disputed claims and other exceptions
  • Notary acknowledgment where your state requires it

Utah rules that this document follows

Statutory waiver formRequired — Utah Code § 38-1a-802(4)Source: Utah Code § 38-1a-802(4)
NotarizationNot required by statute; notarizing is optionalSource: Utah Code § 38-1a-802(4)
Advance waiverVoid — A claimant's written consent that waives or limits lien rights is enforceable only if the claimant executes a statutory waiver and release (or a statutory restrictive endorsement on a check) and receives payment of the amount identified in it; for a progress payment, only to the extent of the payment.Source: Utah Code § 38-1a-802(2)
Governing lien statuteUtah Code §§ 38-1a-101 et seq. (preconstruction and construction liens)Source: Utah Code §§ 38-1a-101 et seq. (preconstruction and construction liens)
If the check bouncesIf the check given in exchange for a waiver and release fails to clear the depository institution on which it is drawn, the waiver and release is void and no lien, bond or contract right is affected.Source: Utah Code § 38-1a-802(3)
RetentionThe statutory progress form does not apply to retention withheld, items or changes pending approval, disputed items and claims, or items furnished or invoiced after the payment period.Source: Utah Code § 38-1a-802(4)(b)

Rules current as of 2026-09-14. Statutes change; verify before relying on them.

How to use this Construction Lien Waiver and Release in Utah

In Utah the waiver form is set by statute (Utah Code § 38-1a-802(4)). Pick the variant that matches the payment — conditional or unconditional, progress or final — and this template prints that statutory form with the exact notice language the law requires. A waiver that departs from the prescribed form can be thrown out, which is why the wording here is reproduced rather than rewritten.

Fill in the amount exactly as it appears on the check or pay application. You give up lien rights only up to that amount, so a mismatch is money left on the table. Set the through date to the last day of work this payment covers, and list retention, disputed extras and anything else you are keeping alive in the exceptions section before you sign.

Do not sign a waiver before the work is furnished: A claimant's written consent that waives or limits lien rights is enforceable only if the claimant executes a statutory waiver and release (or a statutory restrictive endorsement on a check) and receives payment of the amount identified in it; for a progress payment, only to the extent of the payment. (Utah Code § 38-1a-802(2)) Notarization is optional here, but keep a signed copy and send the waiver by a method that leaves a record.

Track the paperwork. Send conditional waivers with every pay application, and only release an unconditional waiver once the funds have cleared your bank. If payment is late, a mechanics lien has its own short deadline — do not let the waiver paperwork distract you from it.

Frequently asked questions

Does Utah have a required lien waiver form?

Yes. Utah prescribes a statutory waiver form (Utah Code § 38-1a-802(4)), and a waiver that does not substantially follow it can be unenforceable. This template reproduces that form and its mandated notice language.

What is the difference between a conditional and an unconditional lien waiver?

A conditional waiver only takes effect when the payment it names actually clears the bank, so it is safe to sign and hand over at the same time as your invoice. An unconditional waiver takes effect the moment you sign it and is enforceable against you even if you are never paid. Send conditional waivers with pay applications; sign unconditional ones only after the funds have settled.

Can I be asked to waive lien rights before I start work?

No. A claimant's written consent that waives or limits lien rights is enforceable only if the claimant executes a statutory waiver and release (or a statutory restrictive endorsement on a check) and receives payment of the amount identified in it; for a progress payment, only to the extent of the payment. (Utah Code § 38-1a-802(2)) A waiver signed before the labor, services or materials are furnished does not bind you.

Does a lien waiver have to be notarized in Utah?

No. No statute requires notarizing a lien waiver in Utah. Notarizing is optional and simply adds proof that the signature is genuine.

What happens to my retention and change orders?

A progress waiver should never release retention or pending change orders. List the retention amount and any disputed extras in the exceptions so they survive the waiver. Watch out for fully executed written change orders: in several states they are released automatically unless you list them as an exception.

What if I sign an unconditional waiver and the check bounces?

If the check given in exchange for a waiver and release fails to clear the depository institution on which it is drawn, the waiver and release is void and no lien, bond or contract right is affected. (Utah Code § 38-1a-802(3)) That is the whole risk of an unconditional waiver: in most states it is enforceable against you the moment you sign, whether or not the money arrives. Use a conditional waiver until the funds have actually settled in your account.

Other names

  • lien waiver
  • conditional lien waiver
  • unconditional lien waiver
  • waiver and release of lien
  • partial lien waiver
  • final lien waiver
  • mechanics lien waiver
  • construction lien release
  • progress payment lien waiver
  • contractor lien release

Related documents

Other states

FormsByState provides self-help document templates and general information, not legal advice. We are not a law firm. For advice about your situation consult a licensed attorney in your state.