California Construction Change Order (2026)
A signed amendment to a construction or home improvement contract: what changes, what it adds to or deducts from the price, the revised contract sum, how many days it adds to the schedule, and confirmation that everything else in the contract stays the same.
This preview updates as you type. Blank fields show as ____ .
What this document covers
- Change order number and the contract it amends
- Contractor, licence number and owner
- Project address and the date of the original contract
- What changes, in the owner's and the contractor's words
- Why it changes — owner request, hidden condition, code or design
- Itemized pricing or a lump sum, added or deducted
- Revised contract sum after every previous change order
- Days added to the schedule and the new completion date
- Payment terms for this change alone
- Confirmation that every other contract term stays in force
California rules that this document follows
| Written change order required | Yes — A change-order form for changes or extra work must be incorporated into the home improvement contract and becomes part of the contract only if it is in writing and signed by the parties before any work covered by the change order begins.Source: Cal. Bus. & Prof. Code § 7159(c)(5), (d)(13) |
|---|---|
| Signature before the changed work | Required — the order counts only if signed before the changed work beginsSource: Cal. Bus. & Prof. Code § 7159(c)(5), (d)(13) |
| Price and schedule in the order | The change in price must be stated; the effect on the schedule or completion date must be stated tooSource: Cal. Bus. & Prof. Code § 7159(c)(5), (d)(13) |
| Payment for the change | A contractor may not collect payment for work not yet completed or for materials not yet delivered, so the money for a change order is due as the changed work is performed, not when the order is signed. The down payment limit of $1,000 or 10 percent of the contract price, whichever is less, is set by the same section.Source: Cal. Bus. & Prof. Code § 7159(d)(9)(C), (d)(8) |
| Licence number on the paperwork | Required on the home improvement contract, so it is printed on the change order too — Contractors State License Board (CSLB)Source: Cal. Bus. & Prof. Code §§ 7030, 7159(d)(1) |
| Lien rights for the extra work | Work added by a signed change order is lienable: it counts as labor and materials furnished for the improvement under this state's mechanics lien chapter.Source: Cal. Civ. Code §§ 8000–8848 (works of improvement) |
Rules current as of 2026-09-14. Statutes change; verify before relying on them.
How to use this Construction Change Order in California
A change-order form for changes or extra work must be incorporated into the home improvement contract and becomes part of the contract only if it is in writing and signed by the parties before any work covered by the change order begins. (Cal. Bus. & Prof. Code § 7159(c)(5), (d)(13)) A change order is not a new contract: it names the original contract and its date, describes exactly what changes, prices the change, and says what it does to the completion date. Everything the contract said before stays in force unless this document changes it.
Price the change the way the owner can check it. Line items — quantity times unit price, labour and materials separated — are what survive a dispute; a lump sum belongs on small, obvious work. Say plainly whether the amount is added to the contract or deducted from it, then carry the arithmetic all the way through: original contract sum, plus the net of every earlier change order, plus or minus this one, equals the revised contract sum. That last number is the only price that should appear on the next invoice, on the lender's draw request and in any lien claim.
Deal with time and money in the same document. Write the schedule effect in whole days, even when it is zero — leave it blank and the original completion date usually still binds, which is how a contractor ends up late because of a change the owner asked for. On payment, California law is specific: A contractor may not collect payment for work not yet completed or for materials not yet delivered, so the money for a change order is due as the changed work is performed, not when the order is signed. The down payment limit of $1,000 or 10 percent of the contract price, whichever is less, is set by the same section. (Cal. Bus. & Prof. Code § 7159(d)(9)(C), (d)(8)) A deposit for special-order or custom material is the one sensible exception.
Sign before the changed work starts, and give the owner a copy the same day. In California that sequence is not advice, it is the rule — the order counts only if it is signed before the work it covers begins. Print the contractor's licence number on the amendment as well, because California requires it on the contract this document becomes part of (Cal. Bus. & Prof. Code §§ 7030, 7159(d)(1)). Keep the signed order with the contract, the invoices and the lien waivers — together they are the whole story of what the job cost.
Frequently asked questions
Does California require a change order to be in writing?
Yes. A change-order form for changes or extra work must be incorporated into the home improvement contract and becomes part of the contract only if it is in writing and signed by the parties before any work covered by the change order begins. (Cal. Bus. & Prof. Code § 7159(c)(5), (d)(13))
Can a contractor bill for extra work with no signed change order?
In California that is the hard case, because a change-order form for changes or extra work must be incorporated into the home improvement contract and becomes part of the contract only if it is in writing and signed by the parties before any work covered by the change order begins. (Cal. Bus. & Prof. Code § 7159(c)(5), (d)(13)) Without the signed order the contractor is usually left arguing unjust enrichment, which recovers cost at best and often nothing.
When is the change order money due?
A contractor may not collect payment for work not yet completed or for materials not yet delivered, so the money for a change order is due as the changed work is performed, not when the order is signed. The down payment limit of $1,000 or 10 percent of the contract price, whichever is less, is set by the same section. (Cal. Bus. & Prof. Code § 7159(d)(9)(C), (d)(8)) In practice that means the change is billed as the changed work is performed, on the schedule this form sets out.
Does a change order have to state the new completion date?
In California yes — the statute makes the effect on the schedule part of what a change order has to say (Cal. Bus. & Prof. Code § 7159(c)(5), (d)(13)). Even where no statute says so, leave it out and the original date usually still binds, so a contractor can be late on a deadline the owner's own change made impossible. Write the days, even when the answer is zero.
Can extra work be included in a mechanics lien?
Yes — work added by a signed change order is labor and materials furnished for the improvement under Cal. Civ. Code §§ 8000–8848 (works of improvement). The signed order is what proves both the scope and the amount, so keep it with the contract and the invoices; an unsigned extra is the claim owners defeat most often.
Do I need the licence number on the change order?
In California the licence number is required on the home improvement contract itself (Cal. Bus. & Prof. Code §§ 7030, 7159(d)(1)), and a change order becomes part of that contract, so print it here too — this form does it for you.
Other names
- change order
- construction change order
- contract amendment contractor
- extra work order
- change order form
- work order change
- variation order
- contract modification construction
- remodel change order
- addendum to construction contract
Related documents
- Construction Lien Waiver and Release — California
- Residential Construction Contract (Home Improvement) — California
- Construction Subcontractor Agreement — California
- Certified Payroll (Form WH-347) — California
Other states
- Alabama
- Alaska
- Arizona
- Arkansas
- Colorado
- Connecticut
- Delaware
- District of Columbia
- Florida
- Georgia
- Hawaii
- Idaho
- Illinois
- Indiana
- Iowa
- Kansas
- Kentucky
- Louisiana
- Maine
- Maryland
- Massachusetts
- Michigan
- Minnesota
- Mississippi
- Missouri
- Montana
- Nebraska
- Nevada
- New Hampshire
- New Jersey
- New Mexico
- New York
- North Carolina
- North Dakota
- Ohio
- Oklahoma
- Oregon
- Pennsylvania
- Rhode Island
- South Carolina
- South Dakota
- Tennessee
- Texas
- Utah
- Vermont
- Virginia
- Washington
- West Virginia
- Wisconsin
- Wyoming
FormsByState provides self-help document templates and general information, not legal advice. We are not a law firm. For advice about your situation consult a licensed attorney in your state.
Download your document
Construction Change Order
One-time payment. No subscription, no card on file, no trial.
Single document
$9 one-time
- PDF + Word, no watermark
- Unlimited edits for 90 days
- State-specific disclosures included
7-day pass
$14.99 one-time
- Every document for 7 days
- Unlimited downloads
- Never renews — ends automatically
Pro
$19 /month
- Unlimited documents and downloads
- All 51 jurisdictions
- Cancel in one click
Secure checkout by Stripe. 30-day money-back guarantee.
Already purchased? Your access is restored automatically on this device or after signing in.